| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 314 | Instalacion de Control RL-01/02 de la bomba, | Pieza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRAPO | TRAPO LIMPIO | KGS | 0.200000 | $22.50 | $4.50 |
| CINTA TEFL | CINTA TEFLON DE 3/8" ANCHO | PZA | 0.300000 | $9.00 | $2.70 |
| Suma de Material | $7.20 | ||||
| Mano de Obra | |||||
| CUAD-03. | CUADRILLA DE INSTRUMENTISTA ESPECIALISTAS | JOR | 0.250000 | $5,937.25 | $1,484.31 |
| CUAD-08 | CUADRILLA DE ELECTRICISTA ESPECIALISTA | JOR | 0.166667 | $6,172.15 | $1,028.69 |
| Suma de Mano de Obra | $2,513.01 | ||||
| Herramienta | |||||
| MO02 | HERRAMIENTA MANUAL | (%)mo | 0.050000 | $0.00 | $0.00 |
| M001 | EQUIPOS DE SEGURIDAD | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $2,520.21 |