| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 386 | Instalacion de Bearing, sall, ITEM:125A/C/D, No. de parte:21-008 | Pieza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRAPO | TRAPO LIMPIO | KGS | 0.100000 | $22.50 | $2.25 |
| MAT 4.1756 | GRASA MULTILITIO ANTIFERRANTE | PZA | 0.100000 | $45.00 | $4.50 |
| Suma de Material | $6.75 | ||||
| Mano de Obra | |||||
| CUAD-03. | CUADRILLA DE INSTRUMENTISTA ESPECIALISTAS | JOR | 0.166667 | $5,937.25 | $989.54 |
| Suma de Mano de Obra | $989.54 | ||||
| Herramienta | |||||
| MO02 | HERRAMIENTA MANUAL | (%)mo | 0.050000 | $0.00 | $0.00 |
| M001 | EQUIPOS DE SEGURIDAD | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $996.29 |