| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 168 | Instalacion de Cable, PLC Communications TCP To ABMi cro MOD 71192-1 | Pieza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRAPO | TRAPO LIMPIO | KGS | 0.100000 | $22.50 | $2.25 |
| CINTA.1 | CINTA AISLANTE SCOTCH-33 | PZA | 0.200000 | $30.00 | $6.00 |
| CINTA-2 | CINTA AISLANTE VULCANIZADA | PZA | 0.200000 | $30.00 | $6.00 |
| Suma de Material | $14.25 | ||||
| Mano de Obra | |||||
| CUAD30 | CUADRILLA DE INSTALACION EN SISTEMAS DE CONTROL | JOR | 0.100000 | $9,528.80 | $952.88 |
| Suma de Mano de Obra | $952.88 | ||||
| Herramienta | |||||
| MO02 | HERRAMIENTA MANUAL | (%)mo | 0.050000 | $0.00 | $0.00 |
| M001 | EQUIPOS DE SEGURIDAD | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $967.13 |