| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 165 | Instalacion de Skid, Structural Fab, Generator MOD SD006963 - S- 01W | Pieza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRAPO | TRAPO LIMPIO | KGS | 0.100000 | $22.50 | $2.25 |
| CINTA.1 | CINTA AISLANTE SCOTCH-33 | PZA | 0.200000 | $30.00 | $6.00 |
| CINTA-2 | CINTA AISLANTE VULCANIZADA | PZA | 0.200000 | $30.00 | $6.00 |
| Suma de Material | $14.25 | ||||
| Mano de Obra | |||||
| CUAD 31 | CUADRILLA DE INSTALACION DE ACCESORIOS EN PLANTA DE INYECCION | JOR | 0.250000 | $9,528.80 | $2,382.20 |
| Suma de Mano de Obra | $2,382.20 | ||||
| Herramienta | |||||
| MO02 | HERRAMIENTA MANUAL | (%)mo | 0.050000 | $0.00 | $0.00 |
| M001 | EQUIPOS DE SEGURIDAD | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $2,396.45 |