| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 229 | Instalacion de Servi t Post, 3/8 " x 1 1/8", Copper MOD 57350 | Pieza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRAPO | TRAPO LIMPIO | KGS | 0.020000 | $22.50 | $0.45 |
| Suma de Material | $0.45 | ||||
| Mano de Obra | |||||
| CUAD 31 | CUADRILLA DE INSTALACION DE ACCESORIOS EN PLANTA DE INYECCION | JOR | 0.003333 | $9,528.80 | $31.76 |
| Suma de Mano de Obra | $31.76 | ||||
| Herramienta | |||||
| MO02 | HERRAMIENTA MANUAL | (%)mo | 0.050000 | $0.00 | $0.00 |
| M001 | EQUIPOS DE SEGURIDAD | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQ001 | ANDAMIO PARA TRABAJOS EN ALTURA, MARCA ATLAS MOD. ATLAS. | HORA | 0.010000 | $5.00 | $0.05 |
| TALA | TALADRO ELECTRICO MARCA DEWALL DE 1/2 DE DIAM | HORA | 0.100000 | $0.40 | $0.04 |
| Suma de Equipo | $0.09 | ||||
| Costo Directo | $32.30 |