| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 174 | Instalacion de Bus, Bar , For SCR Modules Tin Plated MOD 41100- 4 | Pieza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRAPO | TRAPO LIMPIO | KGS | 0.020000 | $22.50 | $0.45 |
| Suma de Material | $0.45 | ||||
| Mano de Obra | |||||
| CUAD30 | CUADRILLA DE INSTALACION EN SISTEMAS DE CONTROL | JOR | 0.250000 | $9,528.80 | $2,382.20 |
| Suma de Mano de Obra | $2,382.20 | ||||
| Herramienta | |||||
| MO02 | HERRAMIENTA MANUAL | (%)mo | 0.050000 | $0.00 | $0.00 |
| M001 | EQUIPOS DE SEGURIDAD | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| ANA-2 | ANALIZADOR DIGITAL FLUKE MOD 187 | HORA | 0.010000 | $1.63 | $0.02 |
| EQ001 | ANDAMIO PARA TRABAJOS EN ALTURA, MARCA ATLAS MOD. ATLAS. | HORA | 0.010000 | $5.00 | $0.05 |
| Suma de Equipo | $0.07 | ||||
| Costo Directo | $2,382.72 |