| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| A1-12 | CONSTRUCCION DE ELEMENTO DE CONCRETO F'C=200 KG/CM2 INCLINADO EN FACAHADA EN FORMA DE "U", ARMADO CON VARILLA DEL NUM. 3 A CADA 25 CM. EN AMBOS SENTIDOS, CON DIMENSIONES DE 0.40x1.00 EN 10 CM. DE ESPESOR, INCLUYE: CIMBRA, ACERO Y CONCRETO. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA-3 | MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" | PT | 4.500000 | $7.50 | $33.75 |
| CLAVO | CLAVO | KG | 0.200000 | $13.05 | $2.61 |
| DIESEL | DIESEL | LITRO | 0.850000 | $7.00 | $5.95 |
| ALAMBRE REC | ALAMBRE RECOCIDO CAL. 18 | KG | 0.500000 | $14.00 | $7.00 |
| AGUA | AGUA | M3 | 0.060000 | $35.00 | $2.10 |
| Suma de Material | $51.41 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 11 | (1 OFICIAL CARPINTERO DE OBRA NEGRA + 1AYUDANTE) | JOR | 0.250000 | $621.97 | $155.49 |
| CUAD OC 62 | CUAD. 1 FIERRERO + 1 AYUDANTE DE FIERRERO | jor | 0.100000 | $588.58 | $58.86 |
| CUADRILLA NO.06 | (1 OFICIAL ALBAÑIL + 1 PEON) | JOR | 0.052500 | $621.97 | $32.65 |
| Suma de Mano de Obra | $247.00 | ||||
| Auxiliar | |||||
| ACERO REF | ACERO DE REFUERZO VARIOS DIAMETROS | TON | 0.010500 | $14,603.95 | $153.34 |
| CIMBRA DE MADERA | CIMBRA DE MADERA | M2 | 0.350000 | $133.08 | $46.58 |
| CONCRETO F-C=200 H/O | CONCRETO H.O. F'C=200 KG/CM2, R.N. AGR. MAX. 3/4" | M3 | 0.189000 | $964.20 | $182.23 |
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Auxiliar | $382.15 | ||||
| Costo Directo | $680.57 |