| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| A10-15 | RECIBIR COLADERAS Y/O PASOS EN LOSAS CON CONCRETO F'C=250 KG/CM2, INCLUYE: CIMBRAR ELEMENTO Y COLADO, MATERIALES, MANO DE ONBRA, HERRAMIENTA Y EQUIPO. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA | M3 | 0.060000 | $35.00 | $2.10 |
| Suma de Material | $2.10 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 11 | (1 OFICIAL CARPINTERO DE OBRA NEGRA + 1AYUDANTE) | JOR | 0.158900 | $621.97 | $98.83 |
| Suma de Mano de Obra | $98.83 | ||||
| Auxiliar | |||||
| CONCRETO F-C=200 H/O | CONCRETO H.O. F'C=200 KG/CM2, R.N. AGR. MAX. 3/4" | M3 | 0.009000 | $964.20 | $8.68 |
| CIMBRA DE MADERA | CIMBRA DE MADERA | M2 | 0.062500 | $133.08 | $8.32 |
| Suma de Auxiliar | $17.00 | ||||
| Costo Directo | $117.93 |