| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| V.024 | REPIZON DE CONCRETO ARMADO SEGUN PROYECTO, f^c= 150 KG/CM2, CIMBRA APARENTE , INCLUYE: GOTERO, MATERIALES, MANO DE OBRA, ACARREOS, HERRAMIENTA, EQUIPO ( P.U.O.T.). | ML. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Concepto | |||||
| 3.5.11.1 | REPISON DE REMATE PARA MURO DE .15 X 0.15 M CON 4 VARS DE 3/8" Y EST. DE #2 @ 20 CMS CONCRETO F´C=150 KG/CM2 Y CIMBRA APARENTE | ML | 1.000000 | $198.07 | $198.07 |
| 3.5.11.1 | REPISON DE REMATE PARA MURO DE .15 X 0.15 M CON 4 VARS DE 3/8" Y EST. DE #2 @ 20 CMS CONCRETO F´C=150 KG/CM2 Y CIMBRA APARENTE | ML | 1.000000 | $198.07 | $198.07 |
| 3.5.11.1 | REPISON DE REMATE PARA MURO DE .15 X 0.15 M CON 4 VARS DE 3/8" Y EST. DE #2 @ 20 CMS CONCRETO F´C=150 KG/CM2 Y CIMBRA APARENTE | ML | 1.000000 | $198.07 | $198.07 |
| 3.5.11.1 | REPISON DE REMATE PARA MURO DE .15 X 0.15 M CON 4 VARS DE 3/8" Y EST. DE #2 @ 20 CMS CONCRETO F´C=150 KG/CM2 Y CIMBRA APARENTE | ML | 1.000000 | $198.07 | $198.07 |
| Suma de Concepto | $792.28 | ||||
| Costo Directo | $792.28 |