| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 259 | SUMINISTRO Y COLOCACION DE ESCOTILLA PASO DE HOMBRE EN CUBIERTA TIPO NB-20 MCA. BILCO DE 0.75 M X 1.40 M., PINTADA CON ESMALTE ANTICORROSIVO COLOR ROJO, INCLUYE: MOLDURAS PERIMETRALES, FIJACION Y SELLADO. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ESCOTILLA 1 | ESCOTILLA PASO HOMBRES MARCA BILCO DE 0.75 X 1.40 M. | PZA | 1.000000 | $12,000.00 | $12,000.00 |
| THINER | THINER | LT | 0.200000 | $12.00 | $2.40 |
| ESMALTE ALKIDALICO | ESMALTE ALKIDALICO SHERWIN WILLIAMS | LT | 0.220000 | $67.00 | $14.74 |
| Suma de Material | $12,017.14 | ||||
| Mano de Obra | |||||
| CUAD OC TEC | CUAD. 1 OF. TECHADOR + 5 AYUDANTES. | jor | 0.700000 | $2,094.25 | $1,465.98 |
| Suma de Mano de Obra | $1,465.98 | ||||
| Auxiliar | |||||
| PRIMARIO ANTICORROSI | PRIMARIO ANTICORROSIVO SYLPYL 53 | LT | 0.200000 | $45.54 | $9.11 |
| Suma de Auxiliar | $9.11 | ||||
| Costo Directo | $13,492.22 |