| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 602 | PROTECCION DE MUROS DE LAS CAMARAS DE REFRIGERACION Y CONGELACION POR EL EXTERIOR A BASE DE PTR DE 2" x 2", VER CROQUIS ANEXO bg | M.L. |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PERFIL PTR | PERFIL ESTRUCTURAL PTR | KG | 11.000000 | $9.50 | $104.50 |
| TAQUETE EXPANSION | TAQUETE EXPANSION | PZA | 3.800000 | $8.00 | $30.40 |
| PLACA DE ACERO | PLACA 1/4" ACERO | KG | 2.300000 | $11.00 | $25.30 |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 0.200000 | $30.00 | $6.00 |
| COMBUSTIBLE 06 | GAS P/ CORTES | KG | 0.100000 | $4.05 | $0.41 |
| COMBUSTIBLE 07 | OXIGENO | M3 | 0.200000 | $40.00 | $8.00 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.100000 | $31.25 | $3.13 |
| PRIM. ANTICORROSIVO | PRIMARIO ANTICORROSIVO | LT | 0.100000 | $47.00 | $4.70 |
| THINER | THINER | LT | 0.100000 | $12.00 | $1.20 |
| ESMALTE ALKIDALICO | ESMALTE ALKIDALICO SHERWIN WILLIAMS | LT | 0.160000 | $67.00 | $10.72 |
| Suma de Material | $194.35 | ||||
| Mano de Obra | |||||
| CUAD OC PAIL | CUAD. 1 OF. PAILERO + 1 AYUDANTE. | jor | 0.120000 | $783.80 | $94.06 |
| CUAD OC PINT | CUAD. 1 OF. PINTORr + 2 AYUDANTES. | jor | 0.030000 | $1,086.03 | $32.58 |
| CUAD OC 09 | CUAD. 1 OF. ALBA脩IL + 1 PEON | jor | 0.015000 | $764.36 | $11.47 |
| Suma de Mano de Obra | $138.10 | ||||
| Equipo | |||||
| SOLDADURA MILLLER | Soldadora Miller Dimension Mod. 652 | hora | 0.100000 | $29.58 | $2.96 |
| ESMERILADORA | Esmeriladora | HR | 0.100000 | $10.06 | $1.01 |
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 0.100000 | $0.59 | $0.06 |
| Suma de Equipo | $4.02 | ||||
| Costo Directo | $336.48 |