| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 34 | SUMINSTRO Y FABRICACIÓN DE GUARNICION TIPO I PARA VIALIDADES, DE CONCRETO SIMPLE DE F'C= 200 KG/CM2 DE FORMA TRAPEZOIDAL DE 0.15 X 0.20 X 0.40 MTS, INCLUYE: MATERIAL, EQUIPO, HERRAMIENTA Y MANO DE OBRA. | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGREGADO-3 | AGUA POTABLE | M3 | 0.050000 | $30.00 | $1.50 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.300000 | $12.00 | $3.60 |
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 3.280000 | $8.20 | $26.90 |
| ACE#4 | ACERO DE REFUERZO De 1/2" #4 f`y = 4200 kg/ml | kg | 4.100000 | $8.20 | $33.62 |
| CONC.PREMEZ.F-C=200 | CONCRETO PREMEZCLADO F'C= 200 KG/CM2 | M3 | 0.077000 | $991.90 | $76.38 |
| DUELA ECONOMICA 3/4" | Duela Economica 3/4" x 3 1/2" x 8 1/4' | pt | 1.000000 | $4.34 | $4.34 |
| CIMBRAPLAY 16 MM | CIMBRAPLAY 16MM | M2 | 0.175000 | $95.00 | $16.63 |
| DESMOLDANTE | DESMOLDANTE | LT | 0.600000 | $13.80 | $8.28 |
| CLAVO DE 2 1/2" A 3 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.050000 | $13.00 | $0.65 |
| Suma de Material | $171.89 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.100000 | $764.36 | $76.44 |
| Suma de Mano de Obra | $76.44 | ||||
| Costo Directo | $248.32 |