| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 572 | BASE PARA TANQUE DE GAS A BASE DE PTR Y PLACA DE ACERO, INCLUYE: MATERIALES, EQUIPO, HERRAMIENTA Y MANO DE OBRA | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PERFIL PTR | PERFIL ESTRUCTURAL PTR | KG | 190.000000 | $9.50 | $1,805.00 |
| PLACA DE ACERO | PLACA 1/4" ACERO | KG | 9.000000 | $11.00 | $99.00 |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 1.500000 | $30.00 | $45.00 |
| COMBUSTIBLE 06 | GAS P/ CORTES | KG | 2.000000 | $4.05 | $8.10 |
| COMBUSTIBLE 07 | OXIGENO | M3 | 0.800000 | $40.00 | $32.00 |
| DISCO P/DESVASTE | DISCO P DESVASTE | PZA | 0.100000 | $31.25 | $3.13 |
| PRIM. ANTICORROSIVO | PRIMARIO ANTICORROSIVO | LT | 2.000000 | $47.00 | $94.00 |
| THINER | THINER | LT | 1.500000 | $12.00 | $18.00 |
| ESMALTE ALKIDALICO | ESMALTE ALKIDALICO SHERWIN WILLIAMS | LT | 2.400000 | $67.00 | $160.80 |
| Suma de Material | $2,265.03 | ||||
| Mano de Obra | |||||
| CUAD OC PAIL | CUAD. 1 OF. PAILERO + 1 AYUDANTE. | jor | 4.000000 | $783.80 | $3,135.20 |
| CUAD OC PINT | CUAD. 1 OF. PINTORr + 2 AYUDANTES. | jor | 0.800000 | $1,086.03 | $868.82 |
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 1.000000 | $764.36 | $764.36 |
| Suma de Mano de Obra | $4,768.38 | ||||
| Equipo | |||||
| SOLDADURA MILLLER | Soldadora Miller Dimension Mod. 652 | hora | 2.000000 | $29.58 | $59.16 |
| ESMERILADORA | Esmeriladora | HR | 1.000000 | $10.06 | $10.06 |
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 1.000000 | $0.59 | $0.59 |
| Suma de Equipo | $69.81 | ||||
| Costo Directo | $7,103.22 |