| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 46 | FIRME DE COMPRESION DE 20 CM DE ESPESOR DE CONCRETO 250 KG/CM2, ARMADO CON MALLA ELECTROSOLDADA, INCLUYE: HERRAMIENTA, MATERIALES Y MANO DE OBRA. PARA PATIO DE MANIOBRAS | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC.PREMEZ.F-C=250 | Concreto Premezclado F'c=250 Kg/cm2 T.M.A. 3/4" revenimiento tiro directo | M3 | 0.220000 | $1,123.85 | $247.25 |
| MALLA 6/6 10-10 | MALLA ELECTROSOLDADA 6/6 10-10 | M2 | 1.100000 | $11.00 | $12.10 |
| AGREGADO-3 | AGUA POTABLE | M3 | 0.010000 | $30.00 | $0.30 |
| MEMBRANA DE PARAF. | MEMBRANA DE PARAFINA BASE AGUA COLOR BLANCO | lit | 0.150000 | $16.96 | $2.54 |
| CIMBRA METALICA | CIMBRA METALICA(CANAL MONTEN) | ML | 0.001430 | $80.10 | $0.11 |
| POLIETILENOCAL 600 | POLIETILENO EN ROLLO | M2 | 0.012500 | $9.42 | $0.12 |
| PEINE METALICO | PEINE METALICO PARA ACABADO DE CONCRETO | PZA | 0.000500 | $857.58 | $0.43 |
| Suma de Material | $262.85 | ||||
| Mano de Obra | |||||
| CUAD OC 05 | CUAD. 1 ALBAÑIL + 5 PEONES | jor | 0.038462 | $2,051.03 | $78.89 |
| Suma de Mano de Obra | $78.89 | ||||
| Equipo | |||||
| ALLANADORA MECANIC. | ALLANADORA MECANICA CON ASPAS | hora | 0.033330 | $167.37 | $5.58 |
| VIBRADOR P/CONCRETO | Vibrador para concreto Mot. Kohler 4 H.Con operador. | HR | 0.106000 | $58.35 | $6.19 |
| COMPACTADOR DYNAPACA | COMPACTADOR DYNAPAC CA 262 MOTOR 152 HP ANCHO DE RODILLO 2.13 M | HR | 0.003680 | $321.23 | $1.18 |
| REGLA VIBRATORIA | REGLA VIBRATORIA | hora | 0.003571 | $212.37 | $0.76 |
| Suma de Equipo | $13.70 | ||||
| Costo Directo | $355.44 |