| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 446 | FIRME DE COMPRESION DE 5 CM DE ESPESOR DE CONCRETO F'C=250 KG/CM2, ARMADO CON MALLA 66-1010. INCLUYE: HERRAMIENTA, MATERIALES Y MANO DE OBRA. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC.PREMEZ.F-C=250 | Concreto Premezclado F'c=250 Kg/cm2 T.M.A. 3/4" revenimiento tiro directo | M3 | 0.055000 | $1,123.85 | $61.81 |
| MALLA 6/6 10-10 | MALLA ELECTROSOLDADA 6/6 10-10 | M2 | 1.100000 | $11.00 | $12.10 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.010000 | $12.00 | $0.12 |
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 0.200000 | $8.20 | $1.64 |
| FIBRA FEST | FIBRA DE POLIPROPILENO PARA CONCRETO | kg | 0.150000 | $85.76 | $12.86 |
| MEMBRANA DE PARAF. | MEMBRANA DE PARAFINA BASE AGUA COLOR BLANCO | lit | 0.075000 | $16.96 | $1.27 |
| CIMBRA METALICA | CIMBRA METALICA(CANAL MONTEN) | ML | 0.014300 | $80.10 | $1.15 |
| POLIETILENOCAL 600 | POLIETILENO EN ROLLO | M2 | 0.012500 | $9.42 | $0.12 |
| AGREGADO-3 | AGUA POTABLE | M3 | 0.021000 | $30.00 | $0.63 |
| PEINE METALICO | PEINE METALICO PARA ACABADO DE CONCRETO | PZA | 0.000500 | $857.58 | $0.43 |
| Suma de Material | $92.13 | ||||
| Mano de Obra | |||||
| CUAD OC 05 | CUAD. 1 ALBAÑIL + 5 PEONES | jor | 0.030000 | $2,051.03 | $61.53 |
| CUAD OC 62 | CUAD. 1 FIERRERO + 1 AYUDANTE DE FIERRERO | jor | 0.006000 | $764.36 | $4.59 |
| Suma de Mano de Obra | $66.12 | ||||
| Equipo | |||||
| REGLA VIBRATORIA | REGLA VIBRATORIA | hora | 0.003571 | $212.37 | $0.76 |
| ALLANADORA MECANIC. | ALLANADORA MECANICA CON ASPAS | hora | 0.016665 | $167.37 | $2.79 |
| Suma de Equipo | $3.55 | ||||
| Costo Directo | $161.79 |