| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 43 | CONSTRUCCION DE CARPETA DE CONCRETO ASFALTICO DE 05 CMS. DE ESPESOR, INCLUYE. RIEGO DE LIGA CON EMULSION ASFALTICA DE ROMPIMIENTO RAPIDO RR-2K A ARAZON DE 0.5 LT/M2 Y SELLO DE CEMENTO A RAZON DE 1 KG/CM2. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC. ASFALTICO | CON ASFALTICO | M3 | 0.070000 | $1,600.00 | $112.00 |
| Suma de Material | $112.00 | ||||
| Mano de Obra | |||||
| CUAD OC 05 | CUAD. 1 ALBAÑIL + 5 PEONES | jor | 0.007000 | $2,051.03 | $14.36 |
| Suma de Mano de Obra | $14.36 | ||||
| Equipo | |||||
| COMPACTADOR NEUMATIC | hora | 0.016700 | $175.00 | $2.92 | |
| PETROLIZADORA | CAMION PETROLIZADORA | HR | 0.016700 | $678.38 | $11.33 |
| EXTENDEDORA ASFALTO | hora | 0.016700 | $250.00 | $4.18 | |
| COMP BAILARINA | COMPACTADOR MANUAL (BAILARINA) MARCA WACKER MOTOR DE GASOLINA 5 H.P. | HR | 0.016700 | $91.13 | $1.52 |
| COMPACTADOR NEUMATIC | hora | 0.016700 | $175.00 | $2.92 | |
| Suma de Equipo | $22.87 | ||||
| Costo Directo | $149.23 |