| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 731 | Yee Sencilla de PVC 2"x2" | Pza. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| YEE PVC S 51 MM | yee pvc sanitario de norma de 2" de diametro calidad Duralion, Rexolit o similar | pza | 1.000000 | $14.55 | $14.55 |
| PEGAM. TANGIT 500 ML | PEGAMENTO TANGIT 500 ML BAJA PRESION | PZA | 0.040000 | $55.00 | $2.20 |
| LIMPIADOR P/PVC | LIMPIADOR PVC 250ML | BOTE | 0.040000 | $37.80 | $1.51 |
| SEGUETA | SEGUETA ESTANDAR | PZA | 0.020000 | $6.90 | $0.14 |
| LIJA FINA ESMERIL | LIJA FINA ESMERIL | PZA | 0.020000 | $6.80 | $0.14 |
| ESTOPA | ESTOPA | Kg. | 0.015000 | $16.00 | $0.24 |
| Suma de Material | $18.78 | ||||
| Mano de Obra | |||||
| I CUADRILLA PLOMEROS | Cuadrilla plomeros (1 Of. plomero + 1 ayudante) | Jor. | 0.022222 | $835.29 | $18.56 |
| I CUADRILLA 2 PEONES | Cuadrilla 2 peones (2 peones: acarreo, ranuras, excavacion) | Jor. | 0.005263 | $610.37 | $3.21 |
| Suma de Mano de Obra | $21.77 | ||||
| Costo Directo | $40.55 |