| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 50-S/N-10 | PARA DESPLANTE DE LOS TERRAPLENES, P.U.O.T. | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGREGADO-3 | AGUA | M3 | 0.200000 | $22.00 | $4.40 |
| Suma de Material | $4.40 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 01 | (1 peón). | Jor | 0.009910 | $279.77 | $2.77 |
| Suma de Mano de Obra | $2.77 | ||||
| Equipo | |||||
| MOTOCONFORMADORA | MOTOCONFORMADORA | HR | 0.032260 | $610.39 | $19.69 |
| PIPA DE AGUA | CAMION TANQUE PARA ACARREO DE LIQUIDOS | HR | 0.032320 | $168.09 | $5.43 |
| COMPACTADOR DYNAPACA | COMPACTADOR DYNAPAC | HR | 0.038460 | $257.76 | $9.91 |
| CARGADOR FRONTAL | CARGADOR FRONTAL | HR | 0.022220 | $358.36 | $7.96 |
| CAMION DE VOLTEO. | CAMION DE VOLTEO | HR | 0.031250 | $242.10 | $7.57 |
| ESTACION TOTAL1 | ESTACION TOTAL | HR | 0.045170 | $14.78 | $0.67 |
| Suma de Equipo | $51.23 | ||||
| Costo Directo | $58.41 |