| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 36-1) | COMPACTADA AL CIEN PORCIENTO (100%) | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGREGADO-10 | MAT. PARA BASE 11/2" A FINOS | M3 | 1.300000 | $55.00 | $71.50 |
| AGREGADO-3 | AGUA | M3 | 0.200000 | $22.00 | $4.40 |
| Suma de Material | $75.90 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 01 | (1 peón). | Jor | 0.009910 | $279.77 | $2.77 |
| Suma de Mano de Obra | $2.77 | ||||
| Equipo | |||||
| MOTOCONFORMADORA | MOTOCONFORMADORA | HR | 0.030000 | $610.39 | $18.31 |
| PIPA DE AGUA | CAMION TANQUE PARA ACARREO DE LIQUIDOS | HR | 0.020000 | $168.09 | $3.36 |
| COMPACTADOR DYNAPACA | COMPACTADOR DYNAPAC | HR | 0.030000 | $257.76 | $7.73 |
| CARGADOR FRONTAL | CARGADOR FRONTAL | HR | 0.026930 | $358.36 | $9.65 |
| CAMION DE VOLTEO. | CAMION DE VOLTEO | HR | 0.050000 | $242.10 | $12.11 |
| ESTACION TOTAL1 | ESTACION TOTAL | HR | 0.045170 | $14.78 | $0.67 |
| Suma de Equipo | $51.83 | ||||
| Costo Directo | $130.50 |