| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 31-1) | DE F'C=150 KG/CM2 | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERAPINO3A | MADERA DE PINO DE 3a. | PT | 1.800000 | $7.50 | $13.50 |
| CIMBRA-01 | CIMBRAPLAY | M2 | 1.000000 | $95.00 | $95.00 |
| COMBUSTIBLE 05 | DIESEL | LT | 0.500000 | $5.50 | $2.75 |
| CIMBRA-02 | CLAVO | Kg. | 0.010000 | $11.00 | $0.11 |
| Suma de Material | $111.36 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.700000 | $662.66 | $463.86 |
| CUAD OC 11 | (1 Of. Carpintero O.N. + 1 Ayud.) | jor | 0.700000 | $715.29 | $500.70 |
| Suma de Mano de Obra | $964.57 | ||||
| Auxiliar | |||||
| CONCRETO F-C=150 H/O | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" O 1 1/2" | M3. | 1.137310 | $932.06 | $1,060.04 |
| Suma de Auxiliar | $1,060.04 | ||||
| Costo Directo | $2,135.97 |