| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 45-A) | DE 180 CM2 DE SECCION (E.P.7) | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-01 | ACERO DEL # 3 ( 1/2") AL # 6 (3/4) | KG | 0.900000 | $9.20 | $8.28 |
| CIMBRA-04 | MADERA DE PINO | PT | 0.575300 | $7.50 | $4.31 |
| CIMBRA-01 | CIMBRAPLAY | M2 | 0.046030 | $95.00 | $4.37 |
| CIMBRA-02 | CLAVO | Kg. | 0.115060 | $11.00 | $1.27 |
| Suma de Material | $18.23 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.060000 | $662.66 | $39.76 |
| Suma de Mano de Obra | $39.76 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR CONCRETO | HR | 0.040000 | $21.64 | $0.87 |
| Suma de Equipo | $0.87 | ||||
| Auxiliar | |||||
| CONCRETO F-C=150 H/O | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" O 1 1/2" | M3. | 0.022000 | $932.06 | $20.51 |
| Suma de Auxiliar | $20.51 | ||||
| Costo Directo | $79.36 |