| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CO300-03 | FABRICACIÓN Y COLADO DE CONCRETO VIBRADO Y CURADO DE F´C= 300 KGS/CM2, INCLUYE: CEMENTO TIPO CPO 30 RS, TOMAÑO DE 13 MM, BOMBEADO | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PREME-04 | CONCRETO PREMEZCLADO F'C=300KG/CM2 CON CEMENTO TIPO CPO CON UNA RELACION AGUA-CEMENTO DE 0.55 BOMBEADO | M3 | 1.050000 | $1,000.00 | $1,050.00 |
| CONCRETO PREME-04 | CONCRETO PREMEZCLADO F'C=300KG/CM2 CON CEMENTO TIPO CPO CON UNA RELACION AGUA-CEMENTO DE 0.55 BOMBEADO | M3 | 1.050000 | $1,000.00 | $1,050.00 |
| CONCRETO PREME-06 | CONCRETO BOMBEADO | m3 | 1.050000 | $100.00 | $105.00 |
| CONCRETO PREME-06 | CONCRETO BOMBEADO | m3 | 1.050000 | $100.00 | $105.00 |
| Suma de Material | $2,310.00 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.055560 | $1,827.13 | $101.52 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.055560 | $1,827.13 | $101.52 |
| Suma de Mano de Obra | $203.03 | ||||
| Equipo | |||||
| MAQUINARIA-23 | VIBRADOR PARA CONCRETO MARCA CIPSA MOD MVK4-AA3614 CON MOTOR KOHLER DE 4 HP Y CONJUNTO CABEZAL DE 4.20 MTS. | HR | 0.200000 | $11.97 | $2.39 |
| MAQUINARIA-23 | VIBRADOR PARA CONCRETO MARCA CIPSA MOD MVK4-AA3614 CON MOTOR KOHLER DE 4 HP Y CONJUNTO CABEZAL DE 4.20 MTS. | HR | 0.200000 | $11.97 | $2.39 |
| Suma de Equipo | $4.79 | ||||
| Costo Directo | $2,517.82 |