| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALB.80 | CASTILLO DE CONCRETO F'C= 150 KG/CM² TIPO K DE 15 X 15 CMS. ARMADO CON ARMADURA TIPO ARMEX 12X 12 -4 ACABADO COMUN EN PRETILES. COMPRENDE: CIMBRADO Y DESCMIBRADO, GANCHOS, TRASLAPES Y DESPERDICIOS EN EL ACERO DE REFUERZO, COLADO Y VIBRADO DE CONCRETO. INCLUYE: MATERIALES DE CONSUMO, MANO DE OBRA, HERRAMIENTAS Y DEMÁS CARGOS CORRESPONDIENTES POR UNIDAD DE OBRA TERMINADA | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA 04 | MADERA PINO 3a. | PT** | 1.832400 | $6.00 | $10.99 |
| CIMBRA 04 | MADERA PINO 3a. | PT** | 1.832400 | $6.00 | $10.99 |
| CIMBRA 04 | MADERA PINO 3a. | PT** | 1.832400 | $6.00 | $10.99 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg.** | 0.135000 | $19.13 | $2.58 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg.** | 0.135000 | $19.13 | $2.58 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg.** | 0.135000 | $19.13 | $2.58 |
| ACERO-ARMEX | ARMADURA TIPO ARMEX 12X 12 | ML** | 1.100000 | $14.47 | $15.92 |
| ACERO-ARMEX | ARMADURA TIPO ARMEX 12X 12 | ML** | 1.100000 | $14.47 | $15.92 |
| ACERO-ARMEX | ARMADURA TIPO ARMEX 12X 12 | ML** | 1.100000 | $14.47 | $15.92 |
| COMBUSTIBLE 01 | DIESEL | LT | 0.600000 | $4.71 | $2.83 |
| COMBUSTIBLE 01 | DIESEL | LT | 0.600000 | $4.71 | $2.83 |
| COMBUSTIBLE 01 | DIESEL | LT | 0.600000 | $4.71 | $2.83 |
| ACERO-18 | ALAMBRE RECOCIDO | KG** | 0.200000 | $14.87 | $2.97 |
| ACERO-18 | ALAMBRE RECOCIDO | KG** | 0.200000 | $14.87 | $2.97 |
| ACERO-18 | ALAMBRE RECOCIDO | KG** | 0.200000 | $14.87 | $2.97 |
| Suma de Material | $105.88 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.070000 | $1,251.29 | $87.59 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.070000 | $1,251.29 | $87.59 |
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.070000 | $1,251.29 | $87.59 |
| Suma de Mano de Obra | $262.77 | ||||
| Auxiliar | |||||
| CONCRETO 150 KG/CM2 | CONCRETO DE F'C= 150KG/CM2 HECHO EN OBRA AGREGADO MAXIMO 3/4. | M3 | 0.023620 | $789.00 | $18.64 |
| CONCRETO 150 KG/CM2 | CONCRETO DE F'C= 150KG/CM2 HECHO EN OBRA AGREGADO MAXIMO 3/4. | M3 | 0.023620 | $789.00 | $18.64 |
| CONCRETO 150 KG/CM2 | CONCRETO DE F'C= 150KG/CM2 HECHO EN OBRA AGREGADO MAXIMO 3/4. | M3 | 0.023620 | $789.00 | $18.64 |
| Suma de Auxiliar | $55.91 | ||||
| Costo Directo | $424.56 |