| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 26.13 | VALV RETENCION DE 75 mm.INCLUYE SUMINISTRO, COLOCACION, DESPERDICIO Y ACARREO A 20MTS. DE DISTANCIA Y UNA ALTURA DE 3 MTS. | pieza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| VALV CHECK 75 MM ROS | VALV CHECK 75 MM ROS | PZA | 1.000000 | $1,862.00 | $1,862.00 |
| SELLADOR PERMATEX | Sellador Permatex | PZA | 0.030000 | $18.39 | $0.55 |
| TEFLON 1" | TEFLON 1" | PZA | 0.040000 | $6.18 | $0.25 |
| Suma de Material | $1,862.80 | ||||
| Mano de Obra | |||||
| CUADRILLA PLOMEROS | Cuadrilla de Plomeros | JOR | 0.166667 | $614.61 | $102.44 |
| Suma de Mano de Obra | $102.44 | ||||
| Auxiliar | |||||
| ANDAMIO | ANDAMIO metalicos | DIA | 0.040000 | $17.33 | $0.69 |
| Suma de Auxiliar | $0.69 | ||||
| Costo Directo | $1,965.93 |