| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IE.390 | SUM. Y COLOC. DE LUMINARIA SOBREPONER 70W MASTER COLOR MOD. MCN-702CB MCA. CONSTRULITA | pieza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| LUMINARIA MASTER | LUMINARIA SOBREPONER 70W MASTER COLOR MOD. MCN-702CB MCA. CONSTRULITA | PZA | 1.000000 | $1,616.00 | $1,616.00 |
| TAQUETE SCI 1/4" | TAQUETE TIPO SCI DE 1/4" CLEVIS | PZA | 4.000000 | $2.50 | $10.00 |
| TORNILLO GALV 1/4" | TORNILLO GALV 1/4" | pza | 4.000000 | $0.34 | $1.36 |
| TUERCA GALV. 1/4" | TUERCA GALV. 1/4" | PZA | 4.000000 | $0.14 | $0.56 |
| Suma de Material | $1,627.92 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | JOR | 0.180000 | $650.39 | $117.07 |
| Suma de Mano de Obra | $117.07 | ||||
| Costo Directo | $1,744.99 |