| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALB.230 | RAMPA DE CONCRETO F'C= 250 KG/CM² DE 15 CMS. DE ESPESOR ARMADA CON MALLA 6X6/6X6 COMPRENDE. RELLENOS. INCLUYE MATERIALES DE CONSUMO, MANO DE OBRA, HERRAMIENTAS Y DEMÁS CARGOS CORRESPONDIENTES POR UNIDAD DE OBRA TERMINADA | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-09 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2 | M3** | 0.230000 | $725.00 | $166.75 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2** | 0.100000 | $80.63 | $8.06 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg.** | 0.250000 | $19.13 | $4.78 |
| CIMBRA 04 | MADERA PINO 3a. | PT** | 0.050000 | $6.00 | $0.30 |
| CIMBRA-03 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.250000 | $10.00 | $2.50 |
| ACERO-MALL-01 | MALLA ELECTROSOLDAD 6X6-6/6 | M2** | 0.150000 | $25.51 | $3.83 |
| Suma de Material | $186.22 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.140000 | $527.40 | $73.84 |
| Suma de Mano de Obra | $73.84 | ||||
| Costo Directo | $260.06 |