| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| TUB.20 | SUMINISTRO Y COLOCACIÓN TUBERIA PVC CONDUIT TIPO PESADO 2" INCLUYE: MATERIALES DE CONSUMO, MANO DE OBRA, HERRAMIENTAS Y DEMÁS CARGOS CORRESPONDIENTES POR UNIDAD DE OBRA TERMINADA | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO PVC C 51 MM | TUBERIA PVC CONDUIT TIPO PESADO 2" | ML | 1.020000 | $19.20 | $19.58 |
| PEGAMENTO TANGIT PVC | PEGAMENTO TANGIT PVC BOTE 250 ml | PZA | 0.025000 | $99.81 | $2.50 |
| LIMPIADOR P/PVC | LIMPIADOR PVC 250ML | BOTE | 0.120000 | $17.65 | $2.12 |
| ESTOPA | ESTOPA | KG | 0.080000 | $14.50 | $1.16 |
| SEGUETA | SEGUETA | PZA | 0.080000 | $4.70 | $0.38 |
| Suma de Material | $25.73 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | JOR | 0.019231 | $650.39 | $12.51 |
| Suma de Mano de Obra | $12.51 | ||||
| Costo Directo | $38.24 |