| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IE.300 | SALIDA DE BOMBA DE AGUA 3F-4H INC. DUCTO, CABLE CAL.8, 10 Y MANO DE OBRA.(7.5HP) | sal |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| POLIDUCTO 19 MM | POLIDUCTO 19 MM | ml | 8.200000 | $1.85 | $15.17 |
| CLAVO 1 1/2" | CLAVO 1 1/2" | kg | 0.500000 | $12.20 | $6.10 |
| RAFIA | RAFIA | ml | 1.000000 | $1.20 | $1.20 |
| GUIA ALAMBRE NO 14 | GUIA ALAMBRE NO 14 | ml | 8.000000 | $0.50 | $4.00 |
| CHALUPA PVC 13 MM | CHALUPA DE PVC 13 MM | PZA | 1.000000 | $2.50 | $2.50 |
| CABLE THWLS CAL. 10 | CABLE THWLS CAL. 10 | ml | 8.500000 | $9.72 | $82.62 |
| CABLE THWLS CAL. 8 | CABLE THWLS CAL. 8 | ML | 26.000000 | $16.58 | $431.08 |
| CINTA AISLAR | CINTA AISLAR | PZA | 0.120000 | $10.00 | $1.20 |
| CAPUCHONES NO 10 | CAPUCHONES NO 10 | PZA | 3.000000 | $1.90 | $5.70 |
| Suma de Material | $549.57 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | JOR | 0.200000 | $650.39 | $130.08 |
| Suma de Mano de Obra | $130.08 | ||||
| Costo Directo | $679.65 |