| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4.15 | Rampa de concreto armada con varilla de 3/8" en ambos sentidos con concreto de f'c=200 Kg/cm2 | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CURAFEST ROJO | CURAFEST (MEMBRANA DE CURADO) | LT | 0.300000 | $14.00 | $4.20 |
| Suma de Material | $4.20 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 01 | ( 1 PEON ) | jor | 0.100000 | $261.31 | $26.13 |
| Suma de Mano de Obra | $26.13 | ||||
| Auxiliar | |||||
| 230.11 | CONCRETO PREMEZCLADO F'C=200 KG/CM2 bombeado hasta 24 mts | M3 | 0.105000 | $1,231.41 | $129.30 |
| 230.10 | ACERO DE REFUERZO FY=4200 KG/CM2 VARIOS DIAMETROS EN CIMENTACION.INCLUYE: ACARREOS, TRASLAPES, GANCHOS, ALAMBRE DE AMARRE. | TN | 0.010815 | $14,687.58 | $158.85 |
| Suma de Auxiliar | $288.14 | ||||
| Concepto | |||||
| CIMCC | CIMBRA | M2 | 1.500000 | $152.42 | $228.63 |
| Suma de Concepto | $228.63 | ||||
| Costo Directo | $547.11 |