| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 11.3 | Banca de concreto armada con malla 6X6/10X10 | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CURAFEST ROJO | CURAFEST (MEMBRANA DE CURADO) | LT | 0.300000 | $14.00 | $4.20 |
| MALLA 6/6 10-10 | MALLA ELECTROSOLDADA 6/6 10-10 | M2 | 1.000000 | $15.74 | $15.74 |
| Suma de Material | $19.94 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 13 | (1 Of. Albanil + 5 Peones) | jor | 0.022222 | $1,925.11 | $42.78 |
| Suma de Mano de Obra | $42.78 | ||||
| Auxiliar | |||||
| 230.11 | CONCRETO PREMEZCLADO F'C=200 KG/CM2 bombeado hasta 24 mts | M3 | 0.105000 | $1,231.41 | $129.30 |
| Suma de Auxiliar | $129.30 | ||||
| Concepto | |||||
| CIMCC | CIMBRA | M2 | 1.000000 | $152.42 | $152.42 |
| Suma de Concepto | $152.42 | ||||
| Costo Directo | $344.44 |