| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CUBIERTA-01 | SUMINISTRO, HABILITADO Y COLOCACIÓN DE TUBOS METALICOS DE 1 1/4" CED. 40 Y 30 PARA ESTRUCTURA INCLUYE: LIMPIEZA, PINTURA ESMALTE A DOS MANOS (UNA DE SELLADOR Y DOS DE PINTURA), MATERIALES, CORTES BOCA DE CABALLO, DESPERDICIOS, TRAZO, NIVELACION, SOLDADURA, EQUIPO, HERRAMIENTA Y MANO DE OBRA.(P.U.O.T.). CUALQUIER ALTURA. | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| HERRERIA-005 | FIERRO NEGRO C-40 DE 2" DIAM. | KG | 1.100000 | $12.00 | $13.20 |
| HERRERIA-003 | PLACA DE ACERO 3/8" | KG | 0.012000 | $10.00 | $0.12 |
| HERRERIA-001 | PTR DE 22 COLOR ROJO | KG | 0.115100 | $12.00 | $1.38 |
| HERRERIA-004 | SOLDADURA E-6013 | KG | 0.001000 | $17.21 | $0.02 |
| PINTURA-05 | PRIMARIO ANTICORROSIVO | LT | 0.002000 | $37.66 | $0.08 |
| PINTURA-03 | PINTURA DE ESMALTE COMEX 100 | LT | 0.003000 | $47.18 | $0.14 |
| PINTURA-06 | THINNER | LT. | 0.001000 | $13.38 | $0.01 |
| HERRERIA-002 | DISCO P/DESBASTE | PZA | 0.000500 | $38.00 | $0.02 |
| COMBUSTIBLE 07 | OXIGENO | M3 | 0.002000 | $29.00 | $0.06 |
| COMBUSTIBLE 08 | ACETILENO | M3 | 0.002000 | $65.00 | $0.13 |
| Suma de Material | $15.16 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 22 | (1 OF. Herrero+1 AYUD.) | Jor | 0.010000 | $426.72 | $4.27 |
| CUADRILLA NO. 18 | (1 Of. Pintor +2 Ayudante). | Jor | 0.002000 | $678.93 | $1.36 |
| CUADRILLA N° 343 EM | 1 of.montador + 1 ayudante. | JOR | 0.005000 | $923.94 | $4.62 |
| Suma de Mano de Obra | $10.24 | ||||
| Equipo | |||||
| MAQUINARIA-90 | equipo de oxicorte con 15 ml de manguera | HR | 0.050000 | $6.24 | $0.31 |
| GRUA 20 TON | GRUA DE 20 TON | HR | 0.001500 | $852.60 | $1.28 |
| ESMERILADORA | ESMERILADORA | HR | 0.002000 | $19.43 | $0.04 |
| Suma de Equipo | $1.63 | ||||
| Costo Directo | $27.03 |