| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ESTRU-22 | APLANADO ACABADO FINO CON LLANA DE MADERA EN MUROS A PLOMO Y REGLA CON MEZCLA CEMENTO-ARENA PROP. 1:4 ESPESOR PROMEDIO DE 2 CMS, INCLUYE: DESPERDICIOS, ACARREOS, ANDAMIOS, EQUIPO, HERRAMIENTA Y MANO DE OBRA.(P.U.O.T.) | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGREGADO-003 | AGUA ACARREO INTERNO | M3 | 0.015200 | $40.00 | $0.61 |
| Suma de Material | $0.61 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.090000 | $385.16 | $34.66 |
| Suma de Mano de Obra | $34.66 | ||||
| Auxiliar | |||||
| MORTERO 1.3 | MORTERO CEMENTO ARENA 1;3 | M3 | 0.027000 | $828.32 | $22.36 |
| ANDAMIO 2 MTS | ANDAMIO DE 2.00 MTS DE ALTURA | DIA | 0.083300 | $16.60 | $1.38 |
| Suma de Auxiliar | $23.75 | ||||
| Costo Directo | $59.02 |