| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ELECTRICA-02 | SUMINISTRO Y COLOCACION DE TUBO CONDUIT PDG DIFERENTES DIAMETROS INCLUYE:MATERIAL, MANO DE OBRA, ACARREOS, MERMAS, DESPERDICIOS, HERRAMIENTA, EQUIPO Y LIMPIEZA. TUBO CONDUITDE 21 MM. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ELECTRICO-11 | TUBO C.G.P.G. 21MM. | ML | 1.100000 | $18.80 | $20.68 |
| ELECTRICO | ALAMBRE GUIA GALVANIZADO CALIBRE 16 | ML | 1.050000 | $0.45 | $0.47 |
| HIDRAULICO-18 | SEGUETA STANDAR | PZA | 0.019608 | $7.80 | $0.15 |
| Suma de Material | $21.31 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.020833 | $819.09 | $17.06 |
| Suma de Mano de Obra | $17.06 | ||||
| Auxiliar | |||||
| ANDAMIO IN | MODULO DE 1.55 MTS PARA INSTALACIONES | R/D | 0.033333 | $78.80 | $2.63 |
| Suma de Auxiliar | $2.63 | ||||
| Costo Directo | $41.00 |