| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ELECTRICA-03 | SUMINISTRO Y COLOCACION DE TUBO CONDUIT PDG DIFERENTES DIAMETROS INCLUYE:MATERIAL, MANO DE OBRA, ACARREOS, MERMAS, DESPERDICIOS, HERRAMIENTA, EQUIPO Y LIMPIEZA. TUBO CONDUITDE 27 MM. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ELECTRICO-12 | TUBO C.G.P.G. 27MM. | ML | 1.100000 | $26.00 | $28.60 |
| ELECTRICO | ALAMBRE GUIA GALVANIZADO CALIBRE 16 | ML | 1.050000 | $0.45 | $0.47 |
| HIDRAULICO-18 | SEGUETA STANDAR | PZA | 0.019608 | $7.80 | $0.15 |
| Suma de Material | $29.23 | ||||
| Mano de Obra | |||||
| CUADRILLA BAJA TENSI | Cuadrilla No. 32 (1Of. Electricista,1 Ayudantes) | jor | 0.025000 | $819.09 | $20.48 |
| Suma de Mano de Obra | $20.48 | ||||
| Auxiliar | |||||
| ANDAMIO IN | MODULO DE 1.55 MTS PARA INSTALACIONES | R/D | 0.033333 | $78.80 | $2.63 |
| Suma de Auxiliar | $2.63 | ||||
| Costo Directo | $52.33 |