| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ECIM-001AP/COMU/10MT | CIMBRA APARENTE EN COLUMNAS Y MUROS, HASTA UNA ALTURA MÁXIMA DE 10.00 mts., INCLUYE: CHAFLAN DE 1", HABILITADO, CIMBRADO, DESCIMBRADO, MATERIALES, ACARREOS, HERRAMIENTA, MANO DE OBRA Y DEMÁS CARGOS CORRESPONDIENTES | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 130100-1080 | Chaflan de 3/4"x3/4" x 8 | pza | 0.730000 | $6.00 | $4.38 |
| 130100-1080 | Chaflan de 3/4"x3/4" x 8 | pza | 0.730000 | $6.00 | $4.38 |
| 500165-2010 | Triplay de 1.22x2.44m 16 mm 1c (pieza) | pza | 0.090000 | $420.00 | $37.80 |
| 500165-2010 | Triplay de 1.22x2.44m 16 mm 1c (pieza) | pza | 0.090000 | $420.00 | $37.80 |
| 103247-1125 | Diesel | lt | 0.610000 | $12.95 | $7.90 |
| 103247-1125 | Diesel | lt | 0.610000 | $12.95 | $7.90 |
| 500165-3010 | Duela 1" x4"x8 1/4 | pt | 1.200000 | $14.18 | $17.02 |
| 500165-3010 | Duela 1" x4"x8 1/4 | pt | 1.200000 | $14.18 | $17.02 |
| 130100-1205 | Polin 3 1/2 x3 1/2 x8 1/4 | pt | 1.020000 | $7.85 | $8.01 |
| 130100-1205 | Polin 3 1/2 x3 1/2 x8 1/4 | pt | 1.020000 | $7.85 | $8.01 |
| 130100-1025 | Barrote 1 1/2"x4"x8 1/4 | pt | 1.340400 | $13.83 | $18.54 |
| 130100-1025 | Barrote 1 1/2"x4"x8 1/4 | pt | 1.340400 | $13.83 | $18.54 |
| 125100-2005 | Alambre recocido Calibre 16 | kg | 0.240200 | $11.30 | $2.71 |
| 125100-2005 | Alambre recocido Calibre 16 | kg | 0.240200 | $11.30 | $2.71 |
| 175125-2010 | Clavo c/cabeza de 2 -4 | kg | 0.072300 | $14.00 | $1.01 |
| 175125-2010 | Clavo c/cabeza de 2 -4 | kg | 0.072300 | $14.00 | $1.01 |
| Suma de Material | $194.73 | ||||
| Mano de Obra | |||||
| A100105-2500 | Cuadrilla de carpinteros para cimbras. Incluye : carpintero, ayudante, cabo y herramienta. | Jor | 0.166595 | $1,036.88 | $172.74 |
| A100105-2500 | Cuadrilla de carpinteros para cimbras. Incluye : carpintero, ayudante, cabo y herramienta. | Jor | 0.166595 | $1,036.88 | $172.74 |
| Suma de Mano de Obra | $345.48 | ||||
| Costo Directo | $540.21 |