| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| CIMCB-250 | CONCRETO EN CIMENTACI脫N F'c = 250 Kg/cm2 PREMEZCLADO RESISTENCIA NORMAL VACIADO CON BOMBA, REVENIMIENTO DE 12 cm., AGREGADO M脕XIMO 3/4", INCLUYE: PRUEBAS DE LABORATORIO, MATERIALES, EQUIPO, HERRAMIENTA, MANO DE OBRA, VIBRADO, CURADO Y DEM脕S CARGOS CORRESPONDIENTES. | M3 |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 74.22 | Agua | m3 | 0.030000 | $40.00 | $1.20 |
| 74.22 | Agua | m3 | 0.030000 | $40.00 | $1.20 |
| 135105-1717 | Concreto f'c = 250 kg/cm2 premezclado resistencia normal, revenimiento de 12 cm., agregado m谩ximo 3/4" | m3 | 1.050000 | $1,080.00 | $1,134.00 |
| 135105-1717 | Concreto f'c = 250 kg/cm2 premezclado resistencia normal, revenimiento de 12 cm., agregado m谩ximo 3/4" | m3 | 1.050000 | $1,080.00 | $1,134.00 |
| 135125-1005 | Bombeo de concreto | m3 | 1.050000 | $150.00 | $157.50 |
| 135125-1005 | Bombeo de concreto | m3 | 1.050000 | $150.00 | $157.50 |
| 135150-3130 | Curafest rojo (Fester) | lt | 1.000000 | $31.48 | $31.48 |
| 135150-3130 | Curafest rojo (Fester) | lt | 1.000000 | $31.48 | $31.48 |
| Suma de Material | $2,648.36 | ||||
| Mano de Obra | |||||
| A100105-1515 | Cuadrilla de peones. Incluye : 5 peones, cabo y herramienta. | Jor | 0.125000 | $1,951.01 | $243.88 |
| A100105-1515 | Cuadrilla de peones. Incluye : 5 peones, cabo y herramienta. | Jor | 0.125000 | $1,951.01 | $243.88 |
| Suma de Mano de Obra | $487.75 | ||||
| Equipo | |||||
| C990140-3510 | Vibrador de Concreto mot. gasolina 8 hp Kolher flecha 14 cabezal AA48 de 17/8 (45mm). | Hora | 0.333330 | $57.49 | $19.16 |
| C990140-3510 | Vibrador de Concreto mot. gasolina 8 hp Kolher flecha 14 cabezal AA48 de 17/8 (45mm). | Hora | 0.333330 | $57.49 | $19.16 |
| Suma de Equipo | $38.33 | ||||
| Costo Directo | $3,174.44 |