| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 25.00 | CONSTRUCCION DE GUARNICION DE CONCRETO DE 25 CM DE BASE X 15 CM DE CORONA X 50 CM DE ALTO, F'C= 150 KG/CM2. INCLUYE: CIMBRADO Y DESCIMBRADO,HERRAMIENTA, MATERIALES, MANO DE OBRA, TRAZO, NIVELACION, ACABADO EN ARISTAS CON VOLTEADOR, ACARREOS NECESARIOS, LIMPIEZA DEL ÁREA DE TRABAJO Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN, P.U.O.T. | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| VAR015 | Varilla de acero corrugada 3/8" No. 3 | ton | 0.000596 | $10,000.00 | $5.96 |
| VARILLA NO. 2 | ALAMBRON LISO DE 1/4" ( NO. 2 ) | TON | 0.000380 | $10,000.00 | $3.80 |
| A4BAR012 | Alambre recocido Calibre 18 | kg | 0.017000 | $12.00 | $0.20 |
| CIAMP035 | Barrote 1 1/2" x 4" x 8' | pt | 4.000000 | $11.00 | $44.00 |
| CIAMP055 | Duela 3/4" x 4" x 8' | pt | 1.136800 | $16.02 | $18.21 |
| CLAVO (VARIAS MED.) | CLAVO PARA MADERA VARIAS MEDIDAS | KG | 0.176500 | $15.00 | $2.65 |
| COMBUSTIBLE 01 | DIESEL | LT | 0.200000 | $7.24 | $1.45 |
| CIMB3 | cimbraplay 1.22x2.44 x 16 MM. | PZA | 0.025000 | $320.00 | $8.00 |
| Suma de Material | $84.27 | ||||
| Mano de Obra | |||||
| CALB21 | (1 Of. Albanil + 1 Peón) | JOR | 0.050000 | $1,143.98 | $57.20 |
| CALB7 | CUADRILLA OC 08 (1 OF. CARPINTERO O.N. + 1AYTE.) | JOR | 0.050000 | $1,133.69 | $56.68 |
| Suma de Mano de Obra | $113.88 | ||||
| Auxiliar | |||||
| FCO00131 | Concreto f'c=150kg/cm2, resistencia normal, agregado maximo 40mm., fabricado en obra con revolvedora; incluye: acarreos a 1¦. estacion a 20.00m. | m3 | 0.070000 | $1,010.34 | $70.72 |
| Suma de Auxiliar | $70.72 | ||||
| Costo Directo | $268.88 |