| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| C10.01.01 | TUBERIA DE50 MM (2") DE DIAMETRO,P.U.O.T. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBOPVCSANNORMA50 | Tubo PVC sanitario de norma 50 mm (2 plg) de diámetro marca Rexolit. | ml | 1.010000 | $10.40 | $10.50 |
| YEEPVCSANT 50MM | YEE DE PVC SENCILLA DE PVC SANITARIO DE 50 X 50 MM | PZA | 0.125000 | $3.59 | $0.45 |
| TEEPVCSAN 50MM | TEE DE PVC SENCILLA DE PVC SANITARIO DE 50 MM | PZA | 0.333333 | $4.63 | $1.54 |
| CODOPVCSAN90X50 | CODO PVC SANITARIO DE NORMA DE 90 X 50MM DE DIAMETRO REXOLIT | PZA | 0.250000 | $4.40 | $1.10 |
| CODOPVCSAN45X50 | CODO PVC SANITARIO DE NORMA DE 45 X 50MM DE DIAMETRO REXOLIT | PZA | 0.500000 | $8.40 | $4.20 |
| CONECTOR ESPIGA DE 2 | Adaptador espiga de PVC sanitario 50 mm (2 plg) de diámetro | pza | 0.125000 | $34.00 | $4.25 |
| LIJAESMERILFINA | Lija de esmeril fina | pza | 0.080000 | $15.30 | $1.22 |
| LIMPIADOR PARA PVC | Limpiador para tubo de PVC de 500 ml | pza | 0.080000 | $37.80 | $3.02 |
| PEGTANGITROS500 | Pegamento tangit rosado, bote de 500 ml | pza | 0.040000 | $135.00 | $5.40 |
| SEGUETAD/STAN | SEGUETA DIENTE STANDARD | PZA | 0.090000 | $8.50 | $0.77 |
| ESTOPA | Estopa | kg | 0.070000 | $24.50 | $1.72 |
| SELLADOR PERMATEX | Sellador Permatex | pza | 0.080000 | $19.60 | $1.57 |
| CINTA TEFLON DE 25 | Cinta teflón de 25 mm | pza | 0.010000 | $11.50 | $0.12 |
| TAQ-SCI-1/4" | TAQUETE TIPO SCI DE 1/4" | PZA | 0.666667 | $2.58 | $1.72 |
| VARILLA ROSCADA 1/4" | Varilla roscada de 1/4'' de diámetro x 3.00 m de longitud | pza | 0.400000 | $27.00 | $10.80 |
| TUERCA HEX. 1/4" | Tuerca hexagonal de 1/4'' de diametro | pza | 1.333333 | $0.21 | $0.28 |
| ARAND-GALV-1/4" | Arandela plana galvanizada de 1/4'' | pza | 0.666667 | $0.30 | $0.20 |
| ABRAZ PERA 50 MM | Abrazadera tipo pera F - 269 de 50 mm | pza | 0.666667 | $4.36 | $2.91 |
| Suma de Material | $51.76 | ||||
| Mano de Obra | |||||
| CUADRILLA INST. 01 | Cuadrilla de plomeros ( Plomero + ayudante) | jor | 0.027027 | $1,137.98 | $30.76 |
| Suma de Mano de Obra | $30.76 | ||||
| Auxiliar | |||||
| ANDAMIO | Modulo de 2.1 m | r/d | 0.150000 | $15.88 | $2.38 |
| Suma de Auxiliar | $2.38 | ||||
| Costo Directo | $84.90 |