| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 5.20 | Trabes de concreto preesforzado de 28.60 ml | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TRABE LA TINAJA | Trabes de concreto preesforzado de 28.60 ml | PZA | 1.000000 | $110,640.00 | $110,640.00 |
| Suma de Material | $110,640.00 | ||||
| Auxiliar | |||||
| TRANSTINAJA | TRANSPORTE LA TINAJA | PZA | 1.000000 | $14,735.31 | $14,735.31 |
| MONTATINAJA | MONTAJE LA TINAJA | PZA | 1.000000 | $27,096.28 | $27,096.28 |
| Suma de Auxiliar | $41,831.59 | ||||
| Costo Directo | $152,471.59 |