| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1.39 | Piedra quebrada o gravada de 25 cm de espesor | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PIEDRA | PIEDRA | M3 | 1.400000 | $90.00 | $126.00 |
| PIEDRA | PIEDRA | M3 | 1.400000 | $90.00 | $126.00 |
| PIEDRA | PIEDRA | M3 | 1.400000 | $90.00 | $126.00 |
| Suma de Material | $378.00 | ||||
| Mano de Obra | |||||
| CUAD OC 05 | CUAD. 1 ALBAÑIL + 5 PEONES | jor | 0.028571 | $2,328.66 | $66.53 |
| CUAD OC 05 | CUAD. 1 ALBAÑIL + 5 PEONES | jor | 0.028571 | $2,328.66 | $66.53 |
| CUAD OC 05 | CUAD. 1 ALBAÑIL + 5 PEONES | jor | 0.028571 | $2,328.66 | $66.53 |
| Suma de Mano de Obra | $199.60 | ||||
| Costo Directo | $577.60 |