| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 48 | En camellon central | kg |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SCT-MAT-ACER-02 | Acero del # 3 (1/2") al # 1 1/2" | kg | 1.100000 | $13.00 | $14.30 |
| SCT-MAT-ACER-01 | Alambre recocido no. 16 | kg | 0.030000 | $17.25 | $0.52 |
| Suma de Material | $14.82 | ||||
| Mano de Obra | |||||
| SCT-CUA-09 | Cuadrilla (1 Fierrero + 1 Ayudante) | Jor | 0.006667 | $928.57 | $6.19 |
| Suma de Mano de Obra | $6.19 | ||||
| Herramienta | |||||
| SCT-HERR-01 | Herramienta menor | (%)mo | 0.020000 | $0.00 | $0.00 |
| SCT-HERR-02 | Seguridad industrial | (%)mo | 0.020000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $21.01 |