| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4100 02 | APLANADO CON MORTERO CEMENTO- ARENA 1:5 DE 1.5 CM DE ESPESOR. ACABADO FINO | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO DD | CEMENTO NORMAL GRIS TIPO I EN SACO | TON | 0.003200 | $1,582.61 | $5.06 |
| AGUA | AGUA | M3 | 0.030000 | $25.50 | $0.77 |
| Suma de Material | $5.83 | ||||
| Mano de Obra | |||||
| CUAD OC 02 | CUAD. 2 (1 albañil + 1 peon) | JOR | 0.095000 | $675.54 | $64.18 |
| Suma de Mano de Obra | $64.18 | ||||
| Herramienta | |||||
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.047500 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| MORTERO 1:5 | mortero cemento arena 1:5 | m3 | 0.015750 | $670.88 | $10.57 |
| Suma de Auxiliar | $10.57 | ||||
| Costo Directo | $80.57 |