| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| P.EXT.PAS 05 | PINTURA EN ESTRUCTURA A BASE DE ESMALTE POLIURETANO 3 MILESIMAS DE ESPESOR EN COLOR AZUL CARIBE O BLANCO INCLUYE : LIMPIEZA DE LA SUPERFICIE, HERRAMIENTA, EQUIPO MENOR, ANDAMIOS, LIMPIEZA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCCION. | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PINTURA 01 | BASE ESMALTE POLIURETANO | LT. | 0.005748 | $157.73 | $0.91 |
| PINTURA 02 | CATALIZADOR | LT | 0.001437 | $336.95 | $0.48 |
| PINTURA 03 | REDUCTOR PARA ESMALTE | LT | 0.000359 | $353.05 | $0.13 |
| PINTURA 04 | ACTIVADOR EPOXIMASTIC | LT | 0.000359 | $236.87 | $0.09 |
| ESTOPA | ESTOPA | KG | 0.002994 | $12.54 | $0.04 |
| THINER | THINER | LT | 0.014969 | $12.00 | $0.18 |
| Suma de Material | $1.82 | ||||
| Mano de Obra | |||||
| CUADRILLA -19 | (1 OFICIAL PINTOR + 2 AYUDANTES) | JOR | 0.003333 | $1,044.95 | $3.48 |
| Suma de Mano de Obra | $3.48 | ||||
| Equipo | |||||
| COMPRESOR | EQUIPO PARA APLICAR PINTURA | HR | 0.003333 | $37.00 | $0.12 |
| Suma de Equipo | $0.12 | ||||
| Auxiliar | |||||
| ANDAMIO OC | ANDAMIO METALICO | (%)mo | 0.040000 | $0.00 | $0.00 |
| Suma de Auxiliar | $0.00 | ||||
| Costo Directo | $5.43 |