| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| S/N-05 | ACERO ESTRUCTURAL A-36 | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-ESTRUC-01 | ACERO ESTRUCTURAL A-36 | KG | 1.010000 | $9.30 | $9.39 |
| ACERO-03 | GALVANIZADO EN CALIENTE INCLUYE FLETE ACARREO DE LA PLANTA A LA OBRA | KG | 1.010000 | $5.10 | $5.15 |
| COMBUSTIBLE 03 | GAS PARA CORTE | KG | 0.009000 | $7.82 | $0.07 |
| COMBUSTIBLE 05 | OXIGENO | M3 | 0.017270 | $54.00 | $0.93 |
| ACERO-ESTRUC-03 | SOLDADURA E 7018 | KG | 0.035000 | $18.64 | $0.65 |
| VARIOS-01 | DISCO ABRASIVO PARA METAL DE 8 " | PZA** | 0.006000 | $46.45 | $0.28 |
| VARIOS-02 | CARDA 6" | PZA** | 0.003000 | $55.57 | $0.17 |
| Suma de Material | $16.64 | ||||
| Mano de Obra | |||||
| CUADRILLA N° 341 | 1 of.pailero + 1 ayudante E. | JOR | 0.003000 | $508.88 | $1.53 |
| CUADRILLA N° 342 | 1 of.soldador + 1 ayudante E. | JOR | 0.003000 | $508.88 | $1.53 |
| CUADRILLA N° 343 | 1 of.montador + 4 ayudante A. | JOR | 0.004390 | $1,086.17 | $4.77 |
| Suma de Mano de Obra | $7.82 | ||||
| Equipo | |||||
| MAQUINARIA-94 | SOLDADORA LINCOLN RX-250 | HR* | 0.091114 | $5.94 | $0.54 |
| Suma de Equipo | $0.54 | ||||
| Auxiliar | |||||
| PRIMARIO | PINTURA PRIMARIO ALQUIDALICO | KG | 0.500000 | $36.76 | $18.38 |
| Suma de Auxiliar | $18.38 | ||||
| Costo Directo | $43.39 |