| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3.01.02.026-H.10. | EN CABEZALES, TOPES, BANCOS, PANTALLAS,ALEROS Y DIAFRAGMAS | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-05 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2 | M3** | 1.050000 | $835.00 | $876.75 |
| REVENIMIENTO | REVENIMIENTO PARA BOMBEO | M3 | 1.050000 | $76.50 | $80.33 |
| CIMBRA-04 | MADERA DE PINO | PT** | 7.000000 | $5.62 | $39.34 |
| CIMBRA-01 | CIMBRAPLAY | M2** | 0.650000 | $77.26 | $50.22 |
| CLAVO | CLAVO | Kg.** | 0.020000 | $16.25 | $0.33 |
| CONCRETO PRE-02 | SERVICIO DE BOMBEO | M3** | 1.050000 | $110.00 | $115.50 |
| DESCUENTO DE ACERO | DESCUENTO DE VOLUMEN DE ACERO CON REFERENCIA AL CONCRETO | M3 | 0.000000 | $835.00 | $0.00 |
| DESCUENTO DE ACERO | DESCUENTO DE VOLUMEN DE ACERO CON REFERENCIA AL CONCRETO | M3 | -0.013000 | $835.00 | -$10.86 |
| Suma de Material | $1,151.60 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.120000 | $508.87 | $61.06 |
| Suma de Mano de Obra | $61.06 | ||||
| Equipo | |||||
| MAQUINARIA-23 | VIBRADOR PARA CONCRETO MCA CIPSA CON MOTOR KOHLER 4 CONJUNTO CABEZAL DE 14" | HR* | 0.182229 | $7.66 | $1.40 |
| Suma de Equipo | $1.40 | ||||
| Auxiliar | |||||
| ANDAMIO METAL | ANDAMIO | DIA | 0.150000 | $19.76 | $2.96 |
| Suma de Auxiliar | $2.96 | ||||
| Costo Directo | $1,217.03 |