| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3.01 .02. 026 - H.10 | CONCRETO HIDRAULICO COLADO EN SECO DE F´C= 250 KG/CM2 (047-G.11.a.1) | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-05 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2 | M3** | 1.050000 | $835.00 | $876.75 |
| REVENIMIENTO | REVENIMIENTO PARA BOMBEO | M3 | 1.050000 | $76.50 | $80.33 |
| CONCRETO PRE-02 | SERVICIO DE BOMBEO | M3** | 1.050000 | $110.00 | $115.50 |
| CIMBRA-04 | MADERA DE PINO | PT** | 1.250000 | $5.62 | $7.03 |
| CIMBRA-01 | CIMBRAPLAY | M2** | 1.600000 | $77.26 | $123.62 |
| CLAVO | CLAVO | Kg.** | 0.400000 | $16.25 | $6.50 |
| DESCUENTO DE ACERO | DESCUENTO DE VOLUMEN DE ACERO CON REFERENCIA AL CONCRETO | M3 | -0.013000 | $835.00 | -$10.86 |
| Suma de Material | $1,198.86 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.700000 | $508.87 | $356.21 |
| Suma de Mano de Obra | $356.21 | ||||
| Equipo | |||||
| MAQUINARIA-23 | VIBRADOR PARA CONCRETO MCA CIPSA CON MOTOR KOHLER 4 CONJUNTO CABEZAL DE 14" | HR* | 0.137856 | $7.66 | $1.06 |
| Suma de Equipo | $1.06 | ||||
| Costo Directo | $1,556.13 |