| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| S/N-22 | EN ZAPATA | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-05 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2 | M3** | 1.050000 | $890.00 | $934.50 |
| CIMBRA-04 | MADERA DE PINO | PT** | 4.500000 | $5.62 | $25.29 |
| CIMBRA-01 | CIMBRAPLAY | M2** | 1.000000 | $77.26 | $77.26 |
| CIMBRA-02 | CLAVO | Kg.** | 0.020000 | $11.11 | $0.22 |
| CONCRETO PRE-02 | BOMBA PARA CONCRETO | M3** | 1.000000 | $120.00 | $120.00 |
| Suma de Material | $1,157.27 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.120000 | $439.37 | $52.72 |
| Suma de Mano de Obra | $52.72 | ||||
| Equipo | |||||
| MAQUINARIA-23 | VIBRADOR PARA CONCRETO MCA CIPSA CON MOTOR KOHLER 4 CONJUNTO CABEZAL DE 14" | HR* | 0.182229 | $11.94 | $2.18 |
| Suma de Equipo | $2.18 | ||||
| Auxiliar | |||||
| ANDAMIO 2 MTS | ANDAMIO DE 2.00 MTS DE ALTURA | DIA | 0.150000 | $18.02 | $2.70 |
| Suma de Auxiliar | $2.70 | ||||
| Costo Directo | $1,214.88 |