| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3.01.02.026-H.10-- | CONCRETO HIDRAULICO DE F'C=250 KG/CM2 EN: ( 047-G.11.a.1 ) | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-05 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2 | M3** | 1.020000 | $890.00 | $907.80 |
| CONCRETO PRE-02 | BOMBA PARA CONCRETO | M3** | 1.000000 | $120.00 | $120.00 |
| CIMBRA-04 | MADERA DE PINO | PT** | 1.250000 | $5.62 | $7.03 |
| CIMBRA-01 | CIMBRAPLAY | M2** | 0.200000 | $77.26 | $15.45 |
| CIMBRA-02 | CLAVO | Kg.** | 4.500000 | $11.11 | $50.00 |
| Suma de Material | $1,100.27 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.120000 | $439.37 | $52.72 |
| Suma de Mano de Obra | $52.72 | ||||
| Equipo | |||||
| MAQUINARIA-23 | VIBRADOR PARA CONCRETO MCA CIPSA CON MOTOR KOHLER 4 CONJUNTO CABEZAL DE 14" | HR* | 0.137856 | $11.94 | $1.65 |
| Suma de Equipo | $1.65 | ||||
| Costo Directo | $1,154.64 |