| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-18 | DADOS DE CONCRETO F'C=200 KG/CM2 DE 35X35CM POR 40CM DE ALTURA ARMADO CON 4 PAQUETES DE 2 VAR. DEL No.4 Y ESTRIBOS No.3 @ 15 CM. INCLUYE CIMBRA Y DESCIMBRA, EL PRECIO UNITARIO INCLUYE: MATERIALES MANO DE OBRA Y HERRAMIENTA | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 0.054000 | $723.12 | $39.05 |
| ACERO 04 | ACERO DEL No. 4 | KG | 6.690000 | $6.00 | $40.14 |
| ACERO 03 | ACERO DEL # (3/) | KG | 2.610000 | $6.00 | $15.66 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 3.400000 | $5.00 | $17.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.140000 | $80.00 | $11.20 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 0.800000 | $11.00 | $8.80 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 0.500000 | $10.00 | $5.00 |
| Suma de Material | $136.85 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.030000 | $1,094.57 | $32.84 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.080000 | $448.80 | $35.90 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.070000 | $448.80 | $31.42 |
| Suma de Mano de Obra | $100.16 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.600000 | $15.98 | $9.59 |
| Suma de Equipo | $9.59 | ||||
| Costo Directo | $246.59 |