| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIM-19 | TRABES DE LIGA DE CONCRETO F'C=200KG/CM2 DE 1.10X0.35 M ARMADAS CON 4 PAQUETES DE 2 VARILLAS DEL No.4 (1/2''), ESTRIBOS DEL No.3 (3/8'') A CADA 15CM, INCLUYE CIMBRA Y DESCIMBRA, COLADO, VIBRADO NIVELADO, CURADO, EL PRECIO UNITARIO INCLUYE: MATERIALES MANO DE OBRA Y HERRAMIENTA | ML. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=200 H/O | Concreto f'c=200 kg/cm2 hecho en obra resistencia normal, agregado maximo 3/4" | M3 | 0.423500 | $723.12 | $306.24 |
| ACERO 04 | ACERO DEL No. 4 | KG | 9.560000 | $6.00 | $57.36 |
| ACERO 03 | ACERO DEL # (3/) | KG | 12.460000 | $6.00 | $74.76 |
| CIMBRA 04 | MADERA PINO 3a. | PT | 3.400000 | $5.00 | $17.00 |
| CIMBRA 01 | CIMBRAPLAY 16 MM | M2 | 0.640000 | $80.00 | $51.20 |
| CIMBRA 02 | CLAVO (VARIAS MED.) | Kg. | 1.200000 | $11.00 | $13.20 |
| CONCRETO 04 | DESMOLDANTE SEPAROL DE SIKA | LT | 2.500000 | $10.00 | $25.00 |
| Suma de Material | $544.76 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 0.035000 | $1,094.57 | $38.31 |
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.360000 | $448.80 | $161.57 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | Jor | 0.150000 | $448.80 | $67.32 |
| Suma de Mano de Obra | $267.20 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | HR | 0.600000 | $15.98 | $9.59 |
| Suma de Equipo | $9.59 | ||||
| Costo Directo | $821.55 |